Maximum Stock Level Formula

Maximum Stock Level Formula


Maximum Stock Level formula is given below. This formula has been explained with an example.

Maximum Stock level = Reorder level + reorder Quantity- (Minimum usage x Minimum lead time)


Maximum Stock Level Formula Example


Reorder level of Inventory = 20,000
Reorder Quantity (EOQ) = 15,000
Minimum usage of inventory = 5000
Minimum lead time for arrival = 2 weeks

Solution

Maximum level = Reorder level + reorder Quantity- (minimum usage x minimum lead time)
=20,000 + 15,000- (5000 x2)
=35,000-10000
=15,000

 Significance of Maximum Stock Level Calculation


Holding of stock or inventory is not free; rather holding of stock requires reasonable amount of expenditure or cost. Maximum stock level is calculated for reducing holding cost of the company. Any Stock above maximum stock level is not recommended.

Reasons of Stock level above the maximum Stock level


One of the main reasons is low consumption of stock that has resulted in piling up of stock. Therefore stock level may be controlled either by reducing re order quantity or reducing the re order level.

Important factor for Maximum Stock Level Determination


Important factor for determining the maximum stock level includes the storing or holding cost, space availability, seasonal stock consumption fluctuation etc. Therefore stock level formula just provides a general guidance, therefore management decide the actual stock level on the bases above mentioned factors.

Maximum Stock Level Practice Question


Reorder level of Inventory = 30,000
Reorder Quantity (EOQ) = 6,000
Minimum usage of inventory = 4,000
Minimum lead time for arrival = 3 weeks
Calculate Maximum Stock Level?




7 comments:

  1. the calculations in your solution is incorrect
    Maximum level = Reorder level + reorder Quantity- (minimum usage x minimum lead time)
    =20,000 + 15,000- (5000 x2)
    =35,000-10000
    =15,000

    the answer should be 25000

    ReplyDelete
  2. Please tell me why 15,000 is correct.
    I really thought 3 minus 1 was equal to 2...

    Is this solution missing a step???

    ReplyDelete
  3. Average Stock Level 17,400 units
    Minimum Stock Levek 6,400 units
    Reorder Level 24,000 units
    Minimum Lead Time 11 days

    Find the minimum consumption/usage of the component per day.
    (Please someone give me solution of this question)