Over Absorption Formula
Over
Absorption = Absorbed overhead – Actual Overheads
|
Over Absorption Formula Example
Machine
Hour = 6000
Absorption
Rate = $ 6
Production
Overhead (Actual) = 25,000
Solution
Absorbed
Overhead = Hr x Absorption Rate
= 6000 hr x 6 = 36,000
Over
absorption = 36,000-25,000
=11,000 (Over absorption)
Reasons of Over Absorption
Over
absorption result, because companies use predetermined absorption rate, while actual
overhead may differ from the absorbed overheads.
Over and under absorption
When
absorbed overhead are more than actual overhead, then this is over absorption
situation, when absorbed overhead are less than actual overhead, then this is
under absorption situation.
Absorbed
Overheads > actual Overheads = over absorption overheads
Absorbed
Overheads < actual Overheads = under absorption overheads